How Georgia nuclear project’s big finish went so wrong

VORJJTDGA5YHYUGOXRY7AT2JWIBy Matt Kempner
ajc.com
12/31/21: Early in 2021, crews at Georgia Power’s nuclear expansion site at Plant Vogtle were struggling to find all the leaks in a pool built to hold spent, highly radioactive fuel.

They added air pressure under the floor of the water-filled pool, hoping air bubbles would pinpoint flawed welds. It didn’t work. So an engineer doubled the air pressure.

The result: The pool’s steel floor plates were damaged, rendering them unusable. New ones had to be manufactured. The fixes and rechecks of the pool have taken nearly a year and cost millions of dollars.

It’s been that kind of a year at Plant Vogtle. Though the expansion project was supposed to be close to completion, a series of missteps and botched jobs in recent months has led to more cost overruns, further delays and fresh worries about quality and oversight.

The project has had setbacks almost since it began. But the 2021 revelations highlight how widespread the problems have become.

Read the whole article: Atlanta Journal-Constitution

Share Button

Activists Push Co-owner, MEAG, to End the Insanity of Vogtle Units 3, 4

MEAG-1by Gloria Tatum
9/22/18 APN – On Thursday, September 20, 2018, activists insisted that the Municipal Electric Authority of Georgia (MEAG), a minority co-owner of the pending two new nuclear reactors 3 and 4 at Plant Vogtle, finally abandon the insanity that is their continued involvement in the project.

Since the previous report by Atlanta Progressive News on the Vogtle co-owners, Jacksonville Electric Authority (JEA) has now sued MEAG over the exploding financial cost of continuing construction on Plant Vogtle 3 and 4.

JEA wants out of its Power Purchase Agreement (PPA) which it has with MEAG to buy energy from Vogtle 3 and 4 for the next twenty years.

JEA claims that Vogtle has become too expensive and they can get energy cheaper from other companies in Georgia.

At the MEAG Power Board Meeting, JEA offered MEAG a way out of the Vogtle money vortex and still meet its contractual obligations to the co-owners and PPA partners.

Read the whole article: Atlanta Progressive News

Share Button

PSC Commissioner Moves for Georgia Power to Stop Collecting Nuclear Tax

bubba-2by Gloria Tatum
6/11/17 (APN) ATLANTA — Georgia Public Service Commissioner Lauren “Bubba” McDonald (District 4) filed a motion to give Georgia Power ratepayers a break by asking the company to suspend collecting the nuclear construction tax, or CWIP.

But it had as much chance as a snowball in hell of being honored by the PSC or Georgia Power.  The Commission voted to hold the motion and refer it to the Georgia Attorney General for an opinion, in a four to one vote on June 06, 2017.

“I move that the Commission request that the Company voluntarily agree that as of July 1, 2017, it will stop collecting any financing charges under the Nuclear Construction Cost Recovery (NCCR) tariff,” McDonald’s motion read.

“Effective July 1, 2017, the Company will utilize Allowance for Funds Used During Construction (AFUDC) accounting treatment on the Construction Work in Progress (CWIP) balance of all Unit 3 and 4 capital costs,” the motion stated.

Read the whole article: Atlanta Progressive News

Share Button

GEORGIA: Sinking into the Vogtle Vortex

The expansion of a Georgia nuclear power plant that fired up dreams for a carbon-free nuclear renaissance in the U.S. has turned into a quagmire of setbacks, financial woes, uncertainty and frustration.
Protest_smby Pam Wright
5/23/17: Cornelia Stumpf has had enough.

The Savannah resident joins more than 2 million other Georgia Power customers who collectively pay a reported $23 million a month for the construction of two new and highly controversial nuclear reactors that may never produce a single kilowatt of energy.

The new reactors at the Alvin W. Vogtle Electric Generating Plant, 30 minutes south of Augusta, were the first approved in the U.S. in 30 years, and they were expected to revive the nation’s nuclear power industry, ushering in an era of carbon-free energy to help control climate change. But the expansion at Plant Vogtle has become an expensive boondoggle for the company and its customers.

“What is upsetting to me is, in the end, I’m just one person and it’s added up to $700 in the six years since they began charging it,” says Stumpf, a conscientious consumer of energy who is speaking from her office on a 90-degree afternoon in May with the air conditioner off.

Georgia Power, a subsidiary of the Southern Company, implemented the 7 percent surcharge in 2011 after lawmakers gave the utility permission to charge customers for the construction of the project. The charge appears on consumer’s bill as “Nuclear Construction Cost Recovery.” So far Georgia Power has reportedly collected nearly $2 billion from the surcharge.

Read the whole article: The Weather Channel

Share Button

Activists Seek Emergency PSC Hearing to Reconsider Vogtle Reactors 3, 4

cwip-protestby Gloria Tatum
(APN) ATLANTA 4/24/17— On Tuesday, April 18, 2017, Glenn Carroll, Director of Nuclear Watch South (NWS), filed a request for an emergency public hearing with the Georgia Public Service Commission (PSC) to seek relief for ratepayers from the Construction Work in Progress (CWIP) tax on customers’ electric bills.

Georgia Power ratepayers have been paying in advance for the construction of Plant Vogtle nuclear reactor units 3 and 4 since 2009, because of the Georgia Legislature’s approval of CWIP via Senate Bill 31, which subverts the traditional ratemaking process and undermines the notion of Georgia Power shareholders taking any risk.

Read the whole story: Atlanta Progressive News

 

Share Button

Vogtle’s Nuclear Expansion in Question after Westinghouse Bankruptcy Filing

vogtle-3by Gloria Tatum
(APN) ATLANTA 4/5/17— Westinghouse Electric Corporation, the designer and builder of the AP1000 nuclear reactors under construction in Georgia and South Carolina, has filed for Chapter 11 reorganization bankruptcy, putting the future of the nuclear power industry in jeopardy.

Clean energy advocates hope this bankruptcy will be a wooden stake in the heart of the so-called “nuclear renaissance” that finally kills it, including the incomplete new reactor units 3 and 4 at Plant Vogtle.

Read the whole story: Atlanta Progressive News

Share Button

PSC members rest eyes, ban critical testimony during Vogtle hearing

stan-wiseby Gloria Tatum
Atlanta 12/14/15 — Georgia Public Service Commissioners struggled to maintain a quorum, and apparently also to stay awake, at Georgia Power’s thirteenth semi-annual Vogtle Construction Monitoring Report (VCM) hearing on December 10, 2015.

Two photographs show Commissioner Stan Wise  (District 5) resting his eyes, during one of the many instances in which Atlanta Progressive News observed Wise rest his eyes for a couple minutes or so at a time.

Read the whole article: Atlanta Progressive News

Share Button

More delays for Plant Vogtle

Vogtle.6.13by Walter C. Jones
Atlanta 12/11/15 — Work to add two nuclear reactors to Plant Vogtle is growing further behind schedule, according to experts hired by state regulators to monitor construction who testified Thursday.

William Jacobs, a nuclear engineer who has managed the construction and startup of seven reactors, testified at a hearing before the Public Service Commission that efforts to catch up haven’t been successful. Instead, the commission consultant said delays have gotten worse despite assurances from Georgia Power executives.

Read the whole article: Savannah Morning News

Share Button

Vogtle nukes could encounter more delays, monitors say

Vogtle-constructionby Tom Crawford
Atlanta 12/10/15 — Georgia Power’s two nuclear reactors at Plant Vogtle, already 39 months behind schedule, could encounter further delays before they actually start generating electricity, according to the experts monitoring the project for the Public Service Commission.

The start dates for the new reactors currently are June 2019 for Unit 3 and June 2020 for Unit 4, but the monitors told the PSC Thursday that it was “unlikely” Georgia Power will meet those commercial operation dates.

“From what we’ve seen in the past and what we know has to be done in the future, it will be a challenge to meet those dates,” said Steven D. Roetger, the lead analyst for the PSC.

Read the whole article: Georgia Report

Share Button

More Construction Delays Put Focus on Vogtle Project’s Economics

ENRSE_VogtleDelays

by Scott Judy
ENR 6/24/15 — As continuing construction delays cause financing and related costs to mount, time is starting to put “significant” strain upon the Plant Vogtle nuclear expansion project’s economics, according to recent testimony presented to the Georgia Public Service Commission by Georgia Power, state monitors and others. As a result, considerable discussion at the recent June hearings focused on whether completing the nuclear project still makes economic sense.

Read the whole article: ENRSoutheast

Share Button