Tag Archives: Vogtle

GEORGIA: Sinking into the Vogtle Vortex

The expansion of a Georgia nuclear power plant that fired up dreams for a carbon-free nuclear renaissance in the U.S. has turned into a quagmire of setbacks, financial woes, uncertainty and frustration.
Protest_smby Pam Wright
5/23/17: Cornelia Stumpf has had enough.

The Savannah resident joins more than 2 million other Georgia Power customers who collectively pay a reported $23 million a month for the construction of two new and highly controversial nuclear reactors that may never produce a single kilowatt of energy.

The new reactors at the Alvin W. Vogtle Electric Generating Plant, 30 minutes south of Augusta, were the first approved in the U.S. in 30 years, and they were expected to revive the nation’s nuclear power industry, ushering in an era of carbon-free energy to help control climate change. But the expansion at Plant Vogtle has become an expensive boondoggle for the company and its customers.

“What is upsetting to me is, in the end, I’m just one person and it’s added up to $700 in the six years since they began charging it,” says Stumpf, a conscientious consumer of energy who is speaking from her office on a 90-degree afternoon in May with the air conditioner off.

Georgia Power, a subsidiary of the Southern Company, implemented the 7 percent surcharge in 2011 after lawmakers gave the utility permission to charge customers for the construction of the project. The charge appears on consumer’s bill as “Nuclear Construction Cost Recovery.” So far Georgia Power has reportedly collected nearly $2 billion from the surcharge.

Read the whole article: The Weather Channel

Share Button

Georgia Power profits off Plant Vogtle construction despite cost overruns, delays, and contractor bankruptcy

Vogtle_construction17by Anne Maxwell
WAYNESBORO, Ga. 5/8/17: The construction of two nuclear reactors at Plant Vogtle is years behind schedule and billions over budget. Last month, the contractor, Westinghouse Electric, filed for Chapter 11 bankruptcy protection.

Plant Vogtle employees hundreds of people in Burke County and the temporary contract with Westinghouse expires Friday, which means the project’s future after that is up in the air.

An attorney for Georgia Power, which is one of the main owners of Plant Vogtle, has said all options are on the table. They could totally shut down the project, or build only one of the two reactors they are currently constructing. There has also been talk of converting it to a natural gas plant, but it is not clear whether that would be economical. Or they could continue building despite even higher costs.

But no matter what happens, Georgia Power is still going to make a profit.

Read the whole story and see video: ABC News Channel 6 wjbf.com

Share Button

Activists Seek Emergency PSC Hearing to Reconsider Vogtle Reactors 3, 4

cwip-protestby Gloria Tatum
(APN) ATLANTA 4/24/17— On Tuesday, April 18, 2017, Glenn Carroll, Director of Nuclear Watch South (NWS), filed a request for an emergency public hearing with the Georgia Public Service Commission (PSC) to seek relief for ratepayers from the Construction Work in Progress (CWIP) tax on customers’ electric bills.

Georgia Power ratepayers have been paying in advance for the construction of Plant Vogtle nuclear reactor units 3 and 4 since 2009, because of the Georgia Legislature’s approval of CWIP via Senate Bill 31, which subverts the traditional ratemaking process and undermines the notion of Georgia Power shareholders taking any risk.

Read the whole story: Atlanta Progressive News

 

Share Button

Vendors line up to demand returns from Westinghouse

Vogtle_eye_viewby Kristi E. Swartz
4/20/2017: Roughly 30 vendors have asked Westinghouse Electric Co. to return $35 million in materials and products that the mega-contractor ordered for four nuclear reactors in Georgia and South Carolina before the company filed for Chapter 11 bankruptcy protection, documents show.

At issue are “reclamation of claim” letters, which are routine during a matter of bankruptcy. Broadly, they allow vendors to ask that unpaid materials and goods ordered within 45 days of a bankruptcy filing be set aside and returned.

Read the whole story: E&E News

 

Share Button

Cost of Westinghouse collapse turns up heat on Scana, Southern

summer

by Kristi Swartz
4/14/17: Scana Corp. executives might extend a contract with Westinghouse Electric Co. LLC as the utility decides whether to complete its multibillion-dollar nuclear power expansion in South Carolina.

Meanwhile, Southern Co.’s Georgia Power unit has yet to decide whether it needs more time to figure out how to proceed with its twin reactors under construction in Georgia.

Read the whole story: E&E News

Share Button

Troubled nuclear plant costs rising for Savannah residents

Georgia_Power_ratepayerby Mary Landers
SAVANNAH 4/8/2017: The costs for Georgia Power’s troubled Plant Vogtle are adding up, but not for the utility or its investors.

Instead, ratepayers are already paying for the two new nuclear reactors, both of which may never produce a watt of electricity. How much have customers already dished out? For southside Savannah customer Cornelia Stumpf, the Vogtle bills already total more than $500.

Read the whole story: Savannah Morning News

Share Button

The High Cost of Ignoring Risk

www.usnews.comby Ryan Alexander
4/6/2017: Last week, Westinghouse Electric Co. announced that it will be filing for bankruptcy. Westinghouse, a subdivision of Toshiba Corporation, is in the process of building two AP1000 nuclear reactors for a power plant known as Plant Vogtle in Georgia. In fact, Westinghouse is bankrupt largely because of Vogtle. The project is a mess, and thanks to the $8.3 billion worth of loan-guarantees federal taxpayers have put into the project, courtesy of the Department of Energy, we are the ones who are going to take the hit if the whole things goes belly up.

In 2008, when the project originally applied for a federally backed loan guarantee, it was estimated that the two reactors under construction would begin commercial operation in April 2016 and 2017, respectively, and cost $14.3 billion. Instead of being completed this month, the project is less than halfway done, more than 39 months behind schedule, and at least $3.3 billion over budget. Now this.

Read the whole story: U.S. News

Share Button

Vogtle’s Nuclear Expansion in Question after Westinghouse Bankruptcy Filing

vogtle-3by Gloria Tatum
(APN) ATLANTA 4/5/17— Westinghouse Electric Corporation, the designer and builder of the AP1000 nuclear reactors under construction in Georgia and South Carolina, has filed for Chapter 11 reorganization bankruptcy, putting the future of the nuclear power industry in jeopardy.

Clean energy advocates hope this bankruptcy will be a wooden stake in the heart of the so-called “nuclear renaissance” that finally kills it, including the incomplete new reactor units 3 and 4 at Plant Vogtle.

Read the whole story: Atlanta Progressive News

Share Button

‘Every option’ being looked at for Plant Vogtle after contractor’s bankruptcy

newsEngin.18249486_022215-nuke-price-bs18by Russell Grantham
ATLANTA 3/30/17: A day after its key contractor filed bankruptcy, Georgia Power said Thursday it is looking at all options for what to do with its unfinished Plant Vogtle nuclear project.

“Every option is on the table,” Georgia Power attorney Kevin Green told members of the Georgia Public Service Commission, which regulates the Atlanta-based utility.

Westinghouse Electric, which is supplying the reactors and overseeing construction of two new reactors at Plant Vogtle near Augusta, filed for Chapter 11 Wednesday, largely as a result of billions in losses on the Vogtle project and another in South Carolina.

Read the whole article: Atlanta Journal-Constitution

Share Button

Time for a nuclear apology from your power company

fanningby Matt Kempner
ATLANTA 3/29/17: Sometimes, even rah-rah cheerleading isn’t enough to make a bad situation look good.

That’s a shame for Georgia Power, because the CEO of its parent has tried to make the company’s nuclear misadventure look like a puffy cloud on a pretty spring day.

Four years ago, when the project to expand nuclear power at Plant Vogtle was already more than a year and a half behind schedule, Southern Co. chief executive Tom Fanning declared that work was moving along in “spectacular fashion.” The company said no further delays were expected on the complex .

Last year, with delays and costs having grown dramatically, Fanning said work on the two new nuclear units was going “beautifully.”

Read the whole story: Atlanta Journal-Constitution

Share Button