by Kristi Swartz
6/8/17: Southern Co.’s nuclear expansion project in Georgia was behind schedule even before it got started.
Contractor Westinghouse Electric Co. LLC and the Nuclear Regulatory Commission grappled with design changes for the new AP1000 technology, delaying the agency’s issuance of the major construction license by four months in 2012.
They’ve never been able to catch up.
The delay was small at the time because Southern’s Georgia Power unit and the contractors said they could make up the time in some way. What’s more, the schedule slip meant little compared with the broader story: Georgia Power was restarting the nuclear industry after 30 years with Plant Vogtle.
The twin reactors would start producing electricity in 2016 and 2017.
Read the whole article: E&E News