PSC members rest eyes, ban critical testimony during Vogtle hearing

stan-wiseby Gloria Tatum
Atlanta 12/14/15 — Georgia Public Service Commissioners struggled to maintain a quorum, and apparently also to stay awake, at Georgia Power’s thirteenth semi-annual Vogtle Construction Monitoring Report (VCM) hearing on December 10, 2015.

Two photographs show Commissioner Stan Wise  (District 5) resting his eyes, during one of the many instances in which Atlanta Progressive News observed Wise rest his eyes for a couple minutes or so at a time.

Read the whole article: Atlanta Progressive News

Share Button

More delays for Plant Vogtle

Vogtle.6.13by Walter C. Jones
Atlanta 12/11/15 — Work to add two nuclear reactors to Plant Vogtle is growing further behind schedule, according to experts hired by state regulators to monitor construction who testified Thursday.

William Jacobs, a nuclear engineer who has managed the construction and startup of seven reactors, testified at a hearing before the Public Service Commission that efforts to catch up haven’t been successful. Instead, the commission consultant said delays have gotten worse despite assurances from Georgia Power executives.

Read the whole article: Savannah Morning News

Share Button

Vogtle nukes could encounter more delays, monitors say

Vogtle-constructionby Tom Crawford
Atlanta 12/10/15 — Georgia Power’s two nuclear reactors at Plant Vogtle, already 39 months behind schedule, could encounter further delays before they actually start generating electricity, according to the experts monitoring the project for the Public Service Commission.

The start dates for the new reactors currently are June 2019 for Unit 3 and June 2020 for Unit 4, but the monitors told the PSC Thursday that it was “unlikely” Georgia Power will meet those commercial operation dates.

“From what we’ve seen in the past and what we know has to be done in the future, it will be a challenge to meet those dates,” said Steven D. Roetger, the lead analyst for the PSC.

Read the whole article: Georgia Report

Share Button

More Construction Delays Put Focus on Vogtle Project’s Economics

ENRSE_VogtleDelays

by Scott Judy
ENR 6/24/15 — As continuing construction delays cause financing and related costs to mount, time is starting to put “significant” strain upon the Plant Vogtle nuclear expansion project’s economics, according to recent testimony presented to the Georgia Public Service Commission by Georgia Power, state monitors and others. As a result, considerable discussion at the recent June hearings focused on whether completing the nuclear project still makes economic sense.

Read the whole article: ENRSoutheast

Share Button

Activists Ask Regulators To Reconsider Nuclear Power Units

votglepowerplant_062315

by Molly Samuel
ATLANTA 6/23/15 — Activists are asking Georgia’s energy regulators to reconsider building new nuclear power units at Plant Vogtle. The plant expansion is expected to be complete in 2020 – three years behind schedule.

Georgia Power has to go to the Public Service Commission every six months to get its expenses for construction at Vogtle approved. Right now, the last half of 2014 is under consideration. The PSC holds hearings to find out what’s going on at the plant, then lets Georgia Power pay its contractors.

Outside groups also get to weigh in. On Tuesday, Glenn Carroll, a coordinator for Nuclear Watch South, asked the PSC to consider stopping the process entirely.

“We think the public deserves to know what it would cost to cancel Plant Vogtle and compare that to the $12 billion we have left to spend,” she said.

Read the whole article: WABE 90.1 FM Atlanta’s NPR Station

Share Button

MEAG creating three subsidiaries for Vogtle funding

Vogtle_1-14by Ray Lightner
GRIFFIN 2/8/14 — The Municipal Electric Authority of Georgia (MEAG) is asking the Nuclear Regulatory Commission to allow it to create up to three wholly owned subsidiaries to help MEAG fund the expansion of the Vogtle nuclear power plant.

The expansion, adding reactors 3 and 4, has already been approved, with MEAG as one of the licensed co-owners, along with Southern Nuclear Operating Company, Georgia Power Company, Oglethorpe Power Corporation and the City of Dalton. MEAG owns 22.7 percent, Oglethorp Power owns 30 percent, City of Dalton owns 1.6 percent and Georgia Power owns the rest.

Southern Nuclear Operating Company operates Vogtle and is making the request, which would allow MEAG to create the three subsidiaries, dividing up MEAG’s 22.7 percent share of the electricity generated by the two new reactors.

Read the whole article: Griffin Daily News

Share Button