Tag Archives: Georgia Public Service Commission

Time to decide if you pay more for Georgia’s nuclear debacle

by Matt KempnerVogtle_ajc_8-3-17
11/3/17 ATLANTA: Don’t read beyond this sentence if you don’t pay a power bill in Georgia and never will.

Otherwise, get your wallet out.

There’s a bit of show biz about to start Monday in hearings with elected state regulators. When it’s over, it’s likely to end up costing you and your Georgia descendents for decades to come.

That’s because the only giant, deeply delayed, steeply over-budget nuclear power construction project still underway in the U.S. may well get another wink and pat on the back from Georgia regulators.

So far, Georgia politicians have failed to enact significant consumer protections that would limit a government-enforced monopoly (Georgia Power) from sidestepping the vast majority of risk while raking in extra (extra!) profits on the overruns for the company’s Plant Vogtle expansion.

Elected members of the Georgia Public Service Commission start the first of four days of hearings Monday. It’s Round One in what on paper could be a momentous decision after years of complex construction plagued by unfinished designs, incomplete scheduling, flawed parts and workmanship, insufficient oversight early on and too much worker downtime.

The PSC accepted the setbacks, missteps and busted budget in the past. But now PSC members are faced with their first go/no-go vote since originally approving the project in 2009. That’s because the bankruptcy of Westinghouse, the project’s main contractor, throws significantly more risk and cost into the mix.

Read the whole article: Atlanta Journal-Constitution

Share Button

Georgia Power vs. the law of holes

Plant-Vogtle-construction-2014by Lyle Harris
10/16/17 ATLANTA Georgia Power is likely to get another shot-in-the-arm after announcing plans to complete construction on those ill-fated nuclear reactors at Plant Vogtle near Waynesboro.

A more appropriate response to this epic boondoggle, of course, would be a swift kick in the pants. But don’t count on it.

The Georgia Public Service Commission (PSC) has scheduled hearings on November 6 to discuss the troubled project, Along with the Southern Company (Georgia Power’s corporate parent) and the smaller utilities that are partners on the Plant Vogtle expansion, there’s little reason to worry about some silly old hearings. While the PSC is ostensibly charged with balancing the interests of the utility with those of its customers, the scales are reliably tipped in Georgia Power’s favor.

The planned reactors at Plant Vogtle were supposed to be up and running by now but they’re only about one-third complete. A series of major snafus and setbacks (including the bankruptcy of Westinghouse Electric which designed and was building the reactors) has increased chances that Georgia households will be picking up more of the tab.

Read the whole article: Saporta Report

Share Button

Conservative group taking Georgia Power to task on Vogtle costs overrun

4364312_web1_0901NuclearLeadby Tom Corwin
10/11/17 AUGUSTA: A conservative Georgia group is calling out Georgia Power on the cost overruns on two nuclear reactors at Plant Vogtle and wants to repeal a state law that allows the company to pass along those costs to ratepayers while construction is underway.

The call puts the Atlanta Tea Party Patriots on the side of some more liberal groups opposing the project but President Debbie Dooley said some issues appeal to all sides. The group is also vowing to make it an issue in next year’s Public Service Commission elections.

The Atlanta Tea Party opposed Senate Bill 31 in 2009 that allowed Georgia Power to recoup the nuclear expansion costs at Vogtle and has supported efforts since to repeal it. But with the failure of a somewhat similar project in South Carolina at the V.C. Summer nuclear site, and the ensuing fallout over its ongoing burden on those ratepayers, Dooley said she believes there is renewed momentum to make the change in Georgia.

“I think there is a bigger demand for it this time because it is in the news,” she said. In the past, “I think people wanted to give Georgia Power the benefit of the doubt. But there’s no benefit of the doubt now.”

Read the whole article: Augusta Chronicle

Share Button

Georgia nuke backers scramble for reasons to keep going

newsEngin.19674583_Southern-AGL.JPEG-0b4bdby Matt Kempner
8/26/17 ATLANTA: There’s a mad scramble underway to come up with new reasons for why Georgians should continue to pay billions of dollars to expand nuclear power in the state. National security! Push back against Russia and China! Healthcare!

Seriously? Yeah, if you believe elected officials, who in the next few days are supposed to get new cost estimates and recommendations from the state’s biggest electric provider.

It seemed like only yesterday when Georgia Power convinced politicians on the Georgia Public Service Commission that a primary reason for expanding Plant Vogtle was because it was the cheapest way to cool our homes, charge our iPhones and keep industry chugging.

Proponents can no longer say that without twitching.

Four years ago, the PSC’s outside financial monitor warned that because of cheap natural gas and, to some extent, rising Vogtle costs, “if a decision had to be made today to build a new nuclear project, it would not be justified on the basis of these results.”

Read the whole article: Atlanta Journal-Constitution

Share Button

Georgia Power has nuked their credibility

Vogtle_ajc_8-3-17by Jay Bookman
8/8/17 ATLANTA: It really is hard to believe.

Eight years after Georgia Power officials confidently assured us that they had this nuclear thing figured out, that two new units at Plant Vogtle could be brought in on budget and on time, leading a supposed renaissance in the U.S. nuclear industry, it’s all in danger of collapsing.

The projected cost of those units has almost doubled, to $25 billion and counting. Completion is still years away, and the prime contractor has gone bankrupt. Last month, construction of two similar units in South Carolina, facing similar cost overruns and delays, was abandoned after it became clear that the additional investment needed to complete the units could not be justified.

Now it’s Georgia’s turn.

Read the whole article: Atlanta Journal-Constitution

Share Button

Georgia Power’s nuclear tower teeters; EMCs ‘concerned’

Vogtle_ajc_8-17by Matt Kempner
8/6/17 ATLANTA: Our bumbling aspiration in Georgia to build more nuclear power is looking suspiciously like that wooden block game, Jenga.
You know, the one where you take turns pulling out a block at a time, hoping not to topple the teetering tower.

How many pieces can be pulled out before Georgia Power’s nuclear expansion at Plant Vogtle metaphorically collapses and takes with it billions of dollars in consumer money?

The few remaining blocks left at the project’s base look shaky to me. (Well, except maybe Georgia Power’s eagerness to continue with a project the state ensures will be delightfully profitable for the power company even though Vogtle is billions of dollars over budget and years behind on completion.)

Small community power systems across the state may be the next blocks to be yanked out of the last nuclear plant still under construction in the U.S.

If you happen to notice what just happened across the border in South Carolina, you’ll know what I’m talking about.

Read the whole article: Atlanta Journal-Constitution

Share Button

‘Idle’ workers cited at delayed Vogtle nuclear power project

Unknownby Matt Kempner
6/16/17: Add “idle” workers to the list of troubles at Georgia Power’s struggling nuclear expansion at Plant Vogtle.

Construction workers are supposed to be toiling away on the project that’s already three years behind schedule and falling farther behind.

But a state monitor recently testified that “idle time, early quits and late starts remained high” among construction workers on the first new-from-scratch U.S. nuclear energy project in 30 years.

“Low productivity has been a continuing issue,” according to written testimony by the construction monitor, William Jacobs, and Steven Roetger, a Georgia Public Service Commission staffer assigned to oversight of the project. They cited reviews by a consultant for the project’s contractor.

Attempts to improve the pace of work had little effect on productivity in the last year, they added. In fact, crucial parts of the construction have faced growing delays.

Read the whole article: Atlanta Journal-Constitution

Share Button

Vogtle completion ‘uneconomic,’ Ga. PSC consultants say

moneyreactors-300x300by  Colby Bermel
6/13/17: Consultants to the Georgia Public Service Commission said June 8 that Westinghouse Electric Co. LLC’s bankruptcy has “invalidated” Georgia Power Co.’s cost calculations at its Alvin W. Vogtle Nuclear Plant and it would be “uneconomic” to complete the plant’s expansion.

The consultants also said that if Georgia Power were to continue construction, the Southern Co. subsidiary will spend $3 billion more on Vogtle than what it predicted in a recent report and the plant’s new units will go online three years later than the company anticipates.

Philip Hayet and Lane Kollen, both vice presidents and principals at J. Kennedy and Associates in Roswell, Ga., submitted written testimony to the commission on behalf of its Public Interest Advocacy Staff. The state agency is conducting a review of Georgia Power’s $222 million in Vogtle construction costs during the second half of 2016 for the Vogtle Construction Monitoring Report, or VCM.

Read the whole article: S&P Global Market Intelligence

Share Button

Millions collected from schools, taxpayers for Vogtle construction

2812409_web1_Plant-Vogtleby Thomas Gardiner

6/11/17: Since 2009, Georgia Power customers have been paying up front for construction costs at the Plant Vogtle nuclear expansion.

Some public entities will have paid more than $1 million for construction before a single kilowatt hour of energy is generated by the expansion.

Georgia Power extended its interim agreement with Westinghouse by 24 hours recently to give the two companies time to finalize a transition agreement as the utility company takes over in the wake of the Westinghouse bankruptcy. That bankruptcy was fueled by cost overruns at the Plant Vogtle and VC Summer nuclear expansion projects.

According to legislation passed in 2009, Georgia Power shall collect costs related to nuclear construction financing and interest to support the plant’s construction, even though the project failed to meet its operational deadline in 2016.

Read the whole article: Savannah Morning News

Share Button

PSC Commissioner Moves for Georgia Power to Stop Collecting Nuclear Tax

bubba-2by Gloria Tatum
6/11/17 (APN) ATLANTA — Georgia Public Service Commissioner Lauren “Bubba” McDonald (District 4) filed a motion to give Georgia Power ratepayers a break by asking the company to suspend collecting the nuclear construction tax, or CWIP.

But it had as much chance as a snowball in hell of being honored by the PSC or Georgia Power.  The Commission voted to hold the motion and refer it to the Georgia Attorney General for an opinion, in a four to one vote on June 06, 2017.

“I move that the Commission request that the Company voluntarily agree that as of July 1, 2017, it will stop collecting any financing charges under the Nuclear Construction Cost Recovery (NCCR) tariff,” McDonald’s motion read.

“Effective July 1, 2017, the Company will utilize Allowance for Funds Used During Construction (AFUDC) accounting treatment on the Construction Work in Progress (CWIP) balance of all Unit 3 and 4 capital costs,” the motion stated.

Read the whole article: Atlanta Progressive News